| CA CE (P) DPK/ /2005-2006 | |||||||
| S/No. | Description of work | A/U | Approximate Qty | Unit Rate in Rs. | Total Amount in Rs. | Period of Completion | |
| 1 | 2 | 3 | 4 | 5 | 7 | 9 | |
| 1 | SUPPLY AND STACKING OF STONE METAL 53-20MM SIZE, CHIPS 13.2MM SIZE, STONE CHIPS 11.2MM SIZE AND SAND FOR CARRYING OUT 2.5CM THICK RESURFACING WORK WITH 7.5CM THICK BUSG FOR CORRECTION WORK BETWEEN KM 205.00 TO 222.39 ON MANALI-SARCHU ROAD UNDER 70 RCC SECTOR IN HP STATE | 03 Months from the date of placing Work Order | |||||
| (a) | Crushed Stone metal 53-20mm | Cum | 652.54 | 1000.00 | 652540.00 | ||
| (b) | Crushed Stone Chips 13.2mm | Cum | 2210.26 | 1625.00 | 3591672.50 | ||
| (c) | Crushed Stone Chips 11.2mm | Cum | 1062.72 | 1625.00 | 1726920.00 | ||
| (d) | Crushed Stone dust /coarse sand | Cum | 559.32 | 700.00 | 391524.00 | ||
| G/Total Rs. | 6362656.50 | ||||||
| Say Rs. | 63,62,656.00 | ||||||
| (Rupees sixty three lacs, sixty two thousands, six hundred and fifty six only). | |||||||
| Sd-x-x-x | |||||||
| Signature of Contractor | (KP Singh) | ||||||
| Brig | |||||||
| Dated : Apr 2005 | Chief Engineer | ||||||
| (for and on behalf of president of India) | |||||||
| Accepting Officer | |||||||
| CA CE (P) DPK/ /2005-2006 | |||||||
| S/No. | Description of work | A/U | Approximate Qty | Unit Rate in Rs. | Total Amount in Rs. | Period of Completion | |
| 1 | 2 | 3 | 4 | 5 | 7 | 9 | |
| 1 | SUPPLY AND STACKING OF STONE METAL 53-20MM SIZE, CHIPS 13.2MM SIZE, STONE CHIPS 11.2MM SIZE AND SAND FOR CARRYING OUT 2.5CM THICK RESURFACING WORK WITH 7.5CM THICK BUSG FOR CORRECTION WORK BETWEEN KM 56.00 TO 91.00 ON MANALI-SARCHU ROAD UNDER 67 RCC SECTOR IN HP STATE | 03 Months from the date of placing Work Order | |||||
| (a) | Crushed Stone metal 53-20mm | Cum | 384.52 | 800.00 | 307616.00 | ||
| (b) | Crushed Stone Chips 13.2mm | Cum | 1307.91 | 1250.00 | 1634887.50 | ||
| (c) | Crushed Stone Chips 11.2mm | Cum | 626.21 | 1250.00 | 782762.50 | ||
| (d) | Crushed Stone dust /coarse sand | Cum | 329.59 | 600.00 | 197754.00 | ||
| G/Total Rs. | 2923020.00 | ||||||
| (Rupees twenty nine lacs, twenty three thousands and twenty only). | |||||||
| Sd-x-x-x | |||||||
| Signature of Contractor | (KP Singh) | ||||||
| Brig | |||||||
| Dated : Apr 2005 | Chief Engineer | ||||||
| (for and on behalf of president of India) | |||||||
| Accepting Officer | |||||||